Whirlpool Assembly Line Installation

At a glance

Location: Clyde, Ohio

Company:

GEM Inc

Industry:
Service:
DSCF0364-200x300

Over the last eight years, Whirlpool has trusted GEM Inc. to handle construction projects to increase manufacturing capacity at both the Clyde and Findlay, Ohio locations. Most recently, GEM installed a new washer assembly line at the Clyde facility. “Line 7” is critical to Whirlpool’s business because it produces a new washing machine model.

GEM installed Line 7 — consisting of 820 feet of conveyance — in the existing Whirlpool plant in just six weeks, within the projected budget using 10,000 man-hours with zero safety incidents. On-time completion was imperative to the project success as production had stopped on the previous model to allow time for installation of the new washing machine model line.

Because of our knowledge and history working in the plant and on multiple other production lines, the project work was able to start prior to completion of the final drawings. Hiring another contractor without experience at the facility could have resulted in lost production and the project being weeks behind schedule.

Key project elements:

  • 4 conveyor lines for assembly of tub, top, motor, and control
  • Packaging line
  • Testing stations
  • Main overhead utility structure including all lighting, wireways, receptacles, air headers and tool railing
For more info contact:
Ron Donnal
Vice President, Business Development

From Our Blog

Jul 24 2023

9 Things You Should Require from Your HVAC Service Provider Whether you already have an HVAC...

Apr 07 2021

4 Important HVAC Maintenance Steps If you’ve been putting off building improvements, especially...

Mar 02 2021

Why Being an FM360 Customer Matters At the Total Sports facility in Rossford, heavy snow was...